Multiple Choice
Procurement management refers to management of (circle all that apply)
A) "bought" or "purchased" items for the project
B) design work or services provided by contractors
C) some items that are produced internally
D) off-the-shelf items, whether obtained internally of externally
E) "turnkey" items or systems
Correct Answer: