Multiple Choice
For the next three questions, choose letters of the terms in the following list that best fit the questions.
-Based on the lectures and readings, what are the five essential areas or sections that should be included in every project master plan.
A) risk plan
B) change control plan
C) responsibility matrix
D) SOW/scope/requirements
E) user needs
F) required contents of proposal
G) qualifications/experience of core team
H) contingency plan
I) project proposal
J) feasibility study
K) project schedule
L) proposal deadline
M) documentation plan
N) WBS/work packages
O) project budget
P) RFP
Q) work review/testing plan
Correct Answer:

Verified
Correct Answer:
Verified
Q22: Statement: Procurement management involves selection of the
Q23: Statement: The scope statement specifies the main
Q24: For the next three questions, choose letters
Q25: The statement of work (SOW) appears in:<br>A)
Q26: For the next three questions, choose letters
Q28: Statement: At least two scope statements might
Q29: Statement: When a project is somewhat similar
Q30: Statement: Usually the larger the project, the
Q31: A well-defined task includes (circle all that
Q32: Statement: A work package is used as