For the next three questions, choose letters of the terms in the following list that best fit the questions.
Where (what section or method) in the project master plan are the following questions addressed (Note, some of these terms might also have applied to the above questions; these can be used again.) .
-Who will be involved in or working on the project?


A) risk plan
B) change control plan
C) responsibility matrix
D) SOW/scope/requirements
E) user needs
F) required contents of proposal
G) qualifications/experience of core team
H) contingency plan
I) project proposal
J) feasibility study
K) project schedule
L) proposal deadline
M) documentation plan
N) WBS/work packages
O) project budget
P) RFP
Q) work review/testing plan