Post-Acceptance Issues (Circle All That Apply)

Question 4

Multiple Choice

Post-acceptance issues (circle all that apply) :


A) occur if the end-item is found to be deficient after installation or delivery,
B) occur during system production/build but after the system design has been approved;
C) occur after the customer has accepted the major end-item
D) occur if the delivered end-item is satisfactory but found to not perform fully to the contracted specifications
E) can impact the final payment for the project