Multiple Choice
Two projects, A and B, are scored using three criteria that are weighted in the proportion 0.20, 0.30, and 0.50. Using a 5-point scale for each of the criteria, Project A is scored 5, 3, 2; Project B is scored 5, 2, 5. Circle all of the following that are true:
A) Project A has a weighted rating of 2.9
B) Project A has a weighted rating of 3.33
C) Project B has a weighted rating of 4.1
D) Project B has a weighted rating of 3.33
E) None of the above are correct
Correct Answer:

Verified
Correct Answer:
Verified
Q7: Signing of the contract ordinarily represents<br>A) approval
Q8: A feasibility study<br>A) can be included in
Q9: Statement: So that the user can remain
Q10: Statement: Most proposals are rather brief and
Q11: When planning a project, it is important
Q13: Statement: In most proposals, the first few
Q14: Statement: The practice of fast-tracking involves performing
Q15: Statement: Sustainability matters are addressed in projects
Q16: The contract statement of work (CSOW) defines<br>A)
Q17: Statement: Following project initiation, momentum increases uniformly