Multiple Choice
Part of determining the labor requirements for an international project involves (circle all that apply)
A) the cost of local labor
B) the productivity of local labor
C) the cost of labor from the contractor's home country
D) the productivity of labor from the contractor's home country
Correct Answer:

Verified
Correct Answer:
Verified