With Incremental TPM (Circle All That Are True)

Question 23

Multiple Choice

With Incremental TPM (circle all that are true) :


A) The end-item is implemented in steps, piece by piece.
B) Elements of the end item can be put to use before the entire end-item is completed.
C) The end-item and its increments are fully planned early in the project.

Correct Answer: