During the negotiation process, the project manager
A) must be intimately familiar with the technical details of the proposed system's design and related costs
B) must try to learn about any competitor bidders
C) must be familiar with those parts of the project plan (schedule, work, or price) that are relatively "fixed" and those that can be negotiated
D) try to know as much as possible about the customer's needs and current position
Correct Answer:

Verified
Correct Answer:
Verified
Q14: Contract administration is responsible for<br>A) determining which
Q15: With a Firm Fixed Price Contract (FFP)<br>A)
Q16: Which of the following contracts is most
Q17: The purpose of contract negotiation is to
Q18: Procurement management can involve which if the
Q20: Statement: With a Cost Plus Incentive Fee
Q21: Statement: Major areas of work that must
Q22: Statement: Procurement management involves selection of the
Q23: Statement: The schedule for procured items can
Q24: Items to be procured during the project