Multiple Choice
Which of the following are sources of internal risks in projects (circle all that apply) :
A) The uniqueness of the project.
B) The experience of the project team.
C) Poorly defined customer needs.
D) The level of control exerted by customers and subcontractors over project work
E) The complexity of the end item.
Correct Answer:

Verified
Correct Answer:
Verified
Q16: A system prototype is (circle all that
Q17: A cause and effect diagram is ordinarily
Q18: Statement: The analogy technique for identifying risks
Q19: Which of the following is the first
Q20: Statement: Projects in which activities are intricately
Q22: Statement: A risk in which the expected
Q23: Statement: A project is considered risky only
Q24: Statement: In virtually all projects, both the
Q25: Statement: A risk symptom is a visible,
Q26: Match each of the following definition with