Multiple Choice
Quality planning should be done:
A) only after scheduling the project so that it would be obvious when quality actions such as inspection are needed
B) before scope definition, scheduling and budgeting of the project
C) independently by the quality manager but at the same time as scheduling is done by the project manager
D) as an integrated part of project planning
E) by the project manager just before inspection and testing
Correct Answer:

Verified
Correct Answer:
Verified
Q1: A subcontractor objects to an audit that
Q2: Quality control is best defined as:<br>A) ensuring
Q3: The Pareto principle states that:<br>A) The majority
Q4: The primary purpose of classification of characteristics
Q5: Self control refers to:<br>A) the self-discipline and
Q7: Failure Mode and Effect Analysis is:<br>A) a
Q8: Quality of a product implies:<br>A) high cost
Q9: Configuration management is:<br>A) a process of updating
Q10: Audit refers to:<br>A) financial aspects of a
Q11: Which of the following presents information in