Solved

Given the Total Cost Schedule Below, for Which Unit Is

Question 56

Multiple Choice

Given the total cost schedule below, for which unit is the marginal cost the lowest?
 Output 0123456 Total Cost 20303536404863\begin{array} { | l | l | l | l | l | l | l | l | } \hline \text { Output } & 0 & 1 & 2 & 3 & 4 & 5 & 6 \\\hline \text { Total Cost } & 20 & 30 & 35 & 36 & 40 & 48 & 63 \\\hline\end{array}


A) 2nd
B) 3rd
C) 4th
D) 5th

Correct Answer:

verifed

Verified

Unlock this answer now