Multiple Choice
Howard's program, Ferocious, has been approved. Now, Howard needs to create his Program Work Breakdown Structure, or PWBS. Which if the following are necessary input items to create the PWBS?
A) Benefits realization plan
B) Program scope statement
C) Scope management plan
D) All of the above