Adam is creating program schedule. He is trying to define the program components and the dependencies among those components. Adam realized that some of the program components will be needed only if certain conditions are met along the program schedule. Which diagramming method should Adam use to display those components?
A) Precedence diagramming method (PDM)
B) Conditional diagramming method (CDM)
C) Arrow diagramming method (ADM)
D) Forceful diagramming method (FDM)
Correct Answer:

Verified
Correct Answer: