Multiple Choice
It was Bob's job to figure out the dependencies among the schedule activities. Bob discovered that all these dependencies are of type finish-to-start. Now Bob needs a network diagramming method to display these dependencies. Which should he use?
A) Arrow diagramming method only
B) Precedence diagramming method only
C) Either the PDM or the ADM
D) Critical diagramming method
Correct Answer:

Verified
Correct Answer:
Verified