Multiple Choice
What is a risk response plan for a program an output of?
A) Identify Risks
B) Risk Management Planning and Analysis
C) Qualitative Risks Analysis
D) Plan Risk Responses
Correct Answer:

Verified
Correct Answer:
Verified