Jordi Brahms is double checking to make sure he has all the inputs to the Risk Management Planning and Analysis process accounted for. Which of the following is NOT an input to the Risk Management Planning and Analysis process?
A) PWBS
B) Risk response plan
C) Program schedule
D) Program budget