Multiple Choice
Howie Dix is planning risk management for his program Ventriloquism Is Easy. Which of the statements below is FALSE?
A) A risk register is an input to both qualitative risk analysis and quantitative risk analysis.
B) Quantitative risk analysis can be performed only on the risks on which the qualitative risk analysis has already been performed.
C) An updated risk register is the output of both qualitative risk analysis and quantitative risk analysis.
D) Qualitative risk analysis is usually performed before the quantitative risk analysis.
Correct Answer:

Verified
Correct Answer:
Verified
Q6: Which is NOT an input to the
Q7: A risk response plan for a program
Q8: Microsoft Project is an acceptable Project Management
Q9: Which is NOT an activity that is
Q10: Boris is making a list of tools
Q12: Which of the following processes uses Regulations
Q13: The procurement management plan is an input
Q14: What are the two main types of
Q15: Which of the following processes does the
Q16: The schedule management plan is an output