Multiple Choice
The Develop Program Team process produces which of the following outputs?
A) Staffing management plan and personnel records
B) Performance assessment and updates to team competency assessments
C) Updates to training records and personnel records
D) Performance assessment and personnel records
Correct Answer:

Verified
Correct Answer: