Multiple Choice
Mario Luigi is a program manager and he wants to capture lessons learned before he can perform a certain process. Which process is Mr. Luigi referring to?
A) Make Archive
B) Component Closure
C) Administrative Closure
D) Contract Closure
Correct Answer:

Verified
Correct Answer:
Verified