_________ standards should be in place to ensure that changes to requirements are implemented in a safe and orderly way.
A) change control and configuration management
B) time control and configuration management
C) access control and configuration management
D) quality control and configuration management
Correct Answer:

Verified
Correct Answer:
Verified