Multiple Choice
The activities have zero duration but are assumed to start at the same timeas the first and the end at the same time as the last one is called__________activity.
A) hijacked.
B) heuristic.
C) hammocked.
D) hole.
Correct Answer:

Verified
Correct Answer:
Verified