Multiple Choice
_________ activities on the network diagram have zero duration and use no resources.
A) dangling.
B) dummy.
C) null.
D) zero.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q11: _ is a working model of one
Q12: The statement "Putting more people on a
Q13: An Elaboration of Waterfall which stresses the
Q14: Risk Management consists of _.<br>A)risk analysis and
Q15: _ is an activity bar chart indicating
Q17: In software prototype, partial working model is
Q18: Which are the two levels of development
Q19: Every risk is associated with a likely
Q20: Ranking of the risks and determining risk
Q21: In Software Prototype, _ means copies of