Solved

Which of the Following Best Describes the Cut Construction Method

Question 2

Multiple Choice

Which of the following best describes the cut construction method for earth retaining systems?


A) Walls are constructed from the base of the wall up, following excavation operations
B) Walls are constructed from the top down to the base, concurrent with excavation operations
C) A) and B.
D) None of the above

Correct Answer:

verifed

Verified