Project X at the Ray Company Has a New Project

Question 3

Multiple Choice

Project X at The Ray Company has a new Project Manager. Company management, eager to get their project back on track, hired this new manager 1 month into a 6 week project. The project is flailing. Which best describes why the project may not make its delivery date based on what we know?


A) High level planning wasn't done adequately.
B) The new project manager became involved too late in the process.
C) The project doesn't have management's support.
D) The project doesn't have management's support

Correct Answer: