Multiple Choice
What is a secondary risk?
A) A risk that is not that important
B) Residual risk
C) Force majeure
D) Risk that is highly unlikely to occur
E) Risk caused by another risk response strategy
Correct Answer:

Verified
Correct Answer:
Verified