Multiple Choice
According to the Economic Order Quantity principle, if you wanted to reduce lot size for a part, which of these actions would you take?
A) Reduce machine set up time
B) Reduce raw material cost
C) Reduce part transportation time
D) Reduce quality inspection time
Correct Answer:

Verified
Correct Answer:
Verified