Multiple Choice
As a Foreign Service Officer you are responsible for determining the cumulative effect of several delays in a project. You have access only to the project's bar chart. Which of the following outcomes can be predicted?
A) The cumulative delay cannot be calculated by reviewing only the bar chart because bar charts do not show relationships among activities
B) The cumulative delay is simply the sum of the individual activity delays
C) The cumulative delay can be calculated by adding up the delays in the critical activities, only
D) The cumulative delay cannot be calculated by reviewing only the bar chart because bar charts do not show the duration of all activities
Correct Answer:

Verified
Correct Answer:
Verified
Q78: A capital budget has just been approved
Q79: Successful project management such as arranging a
Q80: As a meeting facilitator, which of the
Q81: If you find yourself leading a team
Q82: Under most cases an employer can lawfully
Q83: As an initial step toward effective team
Q84: Which of the following information would an
Q86: A U.S. post office branch choosing to
Q87: What would be the most appropriate starting
Q88: To measure the progress of projects, managers