A Manager and the Head of Engineering Discuss a Change

Question 36

Multiple Choice

A manager and the head of engineering discuss a change to a major work package. After the meeting, the manager contacts you and tells you to complete the paperwork to make the change. This is an example of:


A) Management attention to scope management.
B) Management planning.
C) A project expediter position.
D) A change control system.

Correct Answer: