    When Should a Risk Be Avoided
Solved

When Should a Risk Be Avoided

Question 17

Question 17

Multiple Choice

When should a risk be avoided?


A) When the risk event has a low probability of occurrence and low impact
B) When the risk event is unacceptable -- generally one with a very high probability of occurrence and high impact
C) When it can be transferred by purchasing insurance
D) none

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q12: Projections and responses to queries are information

Q13: The DBA is<br>A)a person<br>B)a computer device<br>C)a communication

Q14: The analysis and design of application systems

Q15: The concurrent development model is<br>A)Another name for

Q16: General ledger is also referred to as:<br>A)extra

Q18: Mitigating risk could involve<br>A)identifying risks, obtaining insurance

Q19: Computer support to the manager has been

Q20: An example of risk mitigation is:<br>A)Using proven

Q21: The incremental model of software development is<br>A)A

Q22: 1990's saw the introduction of the _

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines