Multiple Choice
The three stages of the change process are:
A) unfreezing, adjustment, and refreezing.
B) adjustment, unfreezing, and refreezing.
C) adjustment, unfreezing, and re-adjustment.
D) adjustment, re-adjustment, and unfreezing.
Correct Answer:

Verified
Correct Answer:
Verified