Multiple Choice
In quality management, which of the following is not an attribute of the cost of nonconformance?
A) Loss of customers
B) Downtime
C) Safety measures
D) Rework
Correct Answer:

Verified
Correct Answer:
Verified
Q11: Project performance consists of<br>A)Time<br>B)Cost<br>C)Quality<br>D)All of the above
Q12: Following are the phases of Project Management
Q13: QC is typically a(n) _ process.<br>A)Management<br>B)Project manager<br>C)Audit<br>D)Inspection
Q14: Which one of the following is not
Q15: Each component of the software product is
Q17: The business case and the justification for
Q18: Which one of the following is not
Q19: How the project work will be carried
Q20: Design phase consist of<br>A)Input received<br>B)Output received<br>C)Both (A)
Q21: The review of the successes and the