Question 4

Question 4

Multiple Choice

A communication management plan identifies the relevant information that should be communicated to:


A) the project team.
B) the project stakeholders.
C) the project board.
D) the project sponsor.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q1: Who has ultimate responsibility for project risk?<br>A)Steering

Q2: A _ is developed using historical cost

Q3: _focuses on developing change -tolerance software.<br>A)Rapid application

Q5: Which of the following is not considered

Q6: Which technique is applicable when other projects

Q7: successful projects recognize the continuous improvment towards

Q8: _milestones occure at the end of the

Q9: The phases of a project life cycle

Q10: _is the critical factor in understanding how

Q11: A project is typically defined in terms

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines