menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Computing
  3. Study Set
    Experiencing MIS Study Set 2
  4. Exam
    Exam 17: Understanding MS Project: Features and Functions
  5. Question
    In the Gantt Chart the Arrows That Point to the Bars
Solved

In the Gantt Chart the Arrows That Point to the Bars

Question 16

Question 16

Multiple Choice

In the Gantt chart the arrows that point to the bars indicate


A) incomplete tasks.
B) activities.
C) resources.
D) dependencies between activities.
E) complete tasks.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q1: Dependent tasks are either predecessors or successors.

Q7: MS Project is best describes as a

Q10: The resource view shows all the tasks

Q12: Resources cannot be added to the tasks

Q14: Dependencies are reflected in the Gantt chart

Q15: Why is MS Project considered a full-service

Q18: What is a dependency between two tasks?

Q19: The default view of MS Project is

Q34: It is not difficult to show all

Q40: A predecessor is a<br>A) task that must

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines