Multiple Choice
The resource usage view allows the project manager to check
A) projected versus actual costs.
B) time to completion.
C) all of the tasks.
D) all of the subtasks.
E) expected work date and hours for an employee.
Correct Answer:

Verified
Correct Answer:
Verified