Multiple Choice
If the risk of a flood occurring in the next 10 years is accepted to 10%, then the return period for design should be
A) 1 + 0.9°10
B) 1 - 0.9°10
C) 1/1?0.9?10
D) 1/1+0.9?10
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q10: The flow-mass curve is graphical representation of<br>A)cumulative
Q11: For an annual flood series arranged in
Q12: Instantaneous unit hydrograph is a hydrograph of<br>i.
Q13: When the drain is over the canal,
Q14: The crest level in a barrage is
Q16: A 6 hours storm had 4 cm
Q17: The shape of recession limb of a
Q18: A levee on flood<br>A)increases the water surface
Q19: The stream which does not have any