Multiple Choice
Which of the following statements are true?
1) A project must always be managed
2) A project does not always require a plan
3) A project must have regular meetings throughout the projectlifespan
4) A project has a limited lifespan.
A) 1, 3
B) 2, 3
C) 1, 4
D) 1, 2, 4
Correct Answer:

Verified
Correct Answer:
Verified