What Does It Mean to Tailor PRINCE2 to the Project

Question 79

Multiple Choice

What does it mean to tailor PRINCE2 to the project environment?
1) Some elements of PRINCE2 should be omitted
2) The principles should be adapted depending on the environment
3) The methods should be adapted to suit the circumstances
4) Blind obedience to project processes should be avoided


A) 1 and 2
B) 2 and 3
C) 1 and 4
D) 3 and 4

Correct Answer: