Multiple Choice
Which of the true is following about projects?
1) They are driven by deliverables
2) They have finite timescales
3) They involve changes to the business capability
4) They have benefits that are usually realized after project closure
A) 1, 2
B) 1, 2, 3
C) 2, 3, 4
D) 1, 2, 4
Correct Answer:

Verified
Correct Answer:
Verified