Multiple Choice
Which of the following are optional when calculating the budget?
1) Costs of Project Management activities
2) Risk Budget
3) Change Budget
4) Cost Tolerances
A) 1, 2
B) 1, 4
C) 2, 3
D) 3, 4
Correct Answer:

Verified
Correct Answer:
Verified