Multiple Choice
In a single bus-bar system there will be complete shut down when
A) fault occurs on the bus itself
B) fault occurs on neutral line
C) two or more faults occur simultaneously
D) fault occurs with respect to earthing
Correct Answer:

Verified
Correct Answer:
Verified