Multiple Choice
Adding more people to a late systems development project will make the project later because ________.
A) allocating tasks becomes easier
B) training new people slows down team members
C) analyzing the system requirements becomes complex
D) budgeting project costs becomes complicated
Correct Answer:

Verified
Correct Answer:
Verified
Q9: Because of the significant risks involved,organizations should
Q11: _ have the final say on whether
Q14: During the _ phase of the SDLC
Q15: One of the reasons for SDLC problems
Q18: The easiest and cheapest time to alter
Q19: The third phase of the systems development
Q29: The _ approach is the classical process
Q33: In a _ installation,the new system runs
Q39: The primary purpose of the requirements analysis
Q52: Information systems involve people and procedures, so