Multiple Choice
Which role is responsible for ensuring the particular benefits relevant to each project can be realised from implementing the outputs from these projects?
A) Programme Manager
B) Project Manager
C) Programme Office
D) Business Change Manager
Correct Answer:

Verified
Correct Answer:
Verified