Planning and scheduling for a lean initiative requires the use of many tools such as affinity diagrams, interrelationship digraphs, tree diagrams, prioritization matrices, matrix diagrams, process decision program (PDPC) charts, and activity network diagrams. To develop a realistic timeline with attainable deadlines which method would be employed?
A) A process decision program chart (PDPC) .
B) A Gantt chart.
C) The critical path method (CPM) .
D) A PERT analysis to determine probabilistic estimates.
Correct Answer:

Verified
Correct Answer:
Verified
Q3: What would be the benefit of lot
Q4: The project charter helps develop the project
Q5: Integrating improvements within the organization is best
Q6: Variation data is commonly displayed in histogram
Q7: The alignment of value-added work fragments means
Q9: Which phase of the DMAIC model has
Q10: What characteristics are commonly displayed in the
Q11: Process benchmarking is the development of data
Q12: Takt time is the time between the
Q13: All of the following are situations in