Multiple Choice
Which project management technique analyzes tasks and the minimum amount of time that is required to complete each task and the entire project?
A) Six Sigma
B) Monte Carlo Technique
C) Logic Network
D) Program Evaluation and Review Technique
Correct Answer:

Verified
Correct Answer: