Multiple Choice
The quantity of coarse aggregate required for RCC (1:3:6) for 20 cubic metres of work is___________
A) 18.24 m3
B) 15.23 m3
C) 24.87 m3
D) 32.45 m3
Correct Answer:

Verified
Correct Answer:
Verified