Multiple Choice
In an activity network diagram, the ________ indicates which tasks depend on the completion of other tasks in the process.
A) critical path
B) slack time
C) task variance
D) project standard deviation
E) precedence relationship
Correct Answer:

Verified
Correct Answer:
Verified