Multiple Choice
In CBR test, the value of CBR is calculated at
A) 2.5 mm penetration only
B) 5 mm penetration only
C) both 2.5 and 5 mm penetration
D) none of these
Correct Answer:

Verified
Correct Answer:
Verified