Multiple Choice
Liquidated damages:
A) must be reasonably related to actual losses that could be suffered
B) need not be related to actual losses that could be suffered
C) must be less than the actual losses that could be suffered
D) are usually much higher than the actual losses that could be suffered
E) are only available in some states
Correct Answer:

Verified
Correct Answer:
Verified