Multiple Choice
Which of the following is not a major task of Exit criteria?
A) checking test logs against the exit criteria specified in test planning.
B) logging the outcome of test execution.
C) assessing if more tests are needed.
D) writing a test summary report for stakeholders.
Correct Answer:

Verified
Correct Answer:
Verified