Multiple Choice
A new clinical information system is being implemented. Project planners have decided to continue the old system for a time while specific units will be targeted for a specific date to switch over to the new system. Which approach is being used?
A) Big-bang conversion
B) Pilot conversion
C) Phased conversion
D) Parallel conversion
Correct Answer:

Verified
Correct Answer:
Verified
Q1: A committee is evaluating several vendors for
Q2: Which conversion is occurring when an agency
Q4: A nurse superuser is part of a
Q5: When comparing the systems life cycle with
Q6: The project committee has moved to the
Q7: An exact duplication of the data on
Q8: A nurse is part of a committee
Q9: An agency involved in testing a new
Q10: A nursing informatics specialist is part of
Q11: An agency committee conducts a needs assessment